帶有移動電站的二等人員掩蔽所戰時通風設計
Wartime ventilation design for second-class personnel shelters with mobile power stations
摘要:
以某項目二等人員掩蔽所為例,分析了帶有移動電站的防護單元戰時通風設計,并探討了目前人防通風設計中存在的問題。提出在設計過程中應累加主要防毒通道和連通移動電站防毒通道面積,給出了設備選用和計算的過程,校核了超壓排氣活門的選用數量。建議配合建筑專業設計時,移動電站宜和掩蔽人數較多的防護單元結合設計。
Abstract:
Taking a second-class personnel shelter as an example, this paper analyses the wartime ventilation design for the protection unit with mobile power stations, and discusses some problems existing in the current civil air defense ventilation design. It is proposed that the area of the main antivirus channel and the antivirus channel connecting the mobile power station should be accumulated. The equipment selection and calculation process are given, and the number of overpressure exhaust valves is checked. It is suggested that when cooperating with the architecture design, the mobile power station should be combined with the protection unit with a large number of masks.
Keywords:civilairdefenseventilation;antiviruschannel;mobilepowerstation;protectionunit;second-classpersonnelshelter